Welcome to the Onshape forum! Ask questions and join in the discussions about everything Onshape.
First time visiting? Here are some places to start:- Looking for a certain topic? Check out the categories filter or use Search (upper right).
- Need support? Ask a question to our Community Support category.
- Please submit support tickets for bugs but you can request improvements in the Product Feedback category.
- Be respectful, on topic and if you see a problem, Flag it.
If you would like to contact our Community Manager personally, feel free to send a private message or an email.
Release Management - How to release a drawing without the part revision
brucebartlett
Member, OS Professional, Mentor, User Group Leader Posts: 2,141 PRO
How do we release a drawing without pushing the part on the drawing to a new revision?
I released all the parts via releasing the top assembly drawing first.
I released all the parts via releasing the top assembly drawing first.
Tagged:
0
Comments
Twitter: @onshapetricks & @babart1977
I went to the effort to collapse the subassemblies so subpart revs were not pushed and selected the subparts and drawings individually on the same release but somehow the Boss 502-405 which is used across 3 assemblies is now at Rev C even though I only selected on the release of the first assembly it was used in. I am not enjoying this whole release management experience.
Twitter: @onshapetricks & @babart1977
This does not seem correct, please file a support ticket.
Best,
Mike
Twitter: @onshapetricks & @babart1977
Is that part in the same document as the assemblies it's used in?
One thing I don't like about the current implementation of the release management is that parts are automatically revision bumped when releasing an assembly in the same document.
A part shouldn't be revision bumped by an assembly if it hasn't actually changed.
Exactly my issue, this not the way it should work in my opinion, I'd almost go as far as say it is a bug. Sounds like improvements are being worked on here. At the moment a lot of messing about to get drawings released without bumping revision on subparts.
Twitter: @onshapetricks & @babart1977
I haven't tried it, yet, but functionality with assemblies could be the same. If the assembly is referencing the current workspace version of the part, all revisions are bumped up together.
So, it seems there's two paths (recommendations?) that could work for different workflows:
That is correct. If you are referencing the most current version of the part (version in main) even if it has not changed from a prior release OnShape will want to revision it. Essentially the releases are a snapshot in time and do not flow through like a conventional PDM vault system. In drawings and assemblies you need to insert the part at the released state or update the version to the released state.
Coming into Onshape, I thought I understand the "snapshot in time" concept, at least as it applied to versions. I think my confusion stemmed from a misunderstanding of the scope of those snapshots. If I'm specifically selecting a drawing for release, I'm intending to take a snapshot of that drawing. There isn't anything in the process that made me stop and realize that the subject of my snapshot is in a dynamic (work-in-progress) state. I think there may be some workflow/UI tweaks that could make this more apparent.
If not, does this mean that all released drawings have to be created after the release has been submitted?
This brings up the issue of the chicken/egg, we use a drawing as a double check on the design file, but that can't be used as a check if it has to be created after the release is made. released parts can't be modified...
Hopefully, there is a way around it.
For you second question: I think this means that you need to release drawings and parts together to keep them in sync, which I have mixed feelings about. I think I'd probably screw this up someone and get off track.
I've got more questions now, too: What if parts and drawings are in different documents? What if the same part is on multiple drawings? Should I be trying to keep my drawing and part revisions in sync?
Edit for my previous comment: Turns out it is possible to update a linked document in a drawing. You have to right-click on the TAB, and select "update linked document" from there.
I feel better now.
On this drawing, I have dropped some extra parts in and you can see how to control them, (it would be nice however to see the part thumbnail image rather the total studio thumbnail). I have also made changes to the bracket in the main workspace which seems to always blow through onto the flat pattern which is confusing and dangerous, I would have thought the flat pattern would follow its parents version.
Twitter: @onshapetricks & @babart1977
Note: watermarks are set from the drawing release, not the part release.